Moving Average Price vs Standard Price in SAP Material Master
Moving Average Price vs Standard Price in SAP Material Master
It is maintained in the accounting view of the material master and configured in Material Type. see below
See the bottom of the below image for price control
First Purchase Order Made for 100 Qty at $20/pcs
Price = 100*20
= 2000$
Second Purchase Order Made for 500 Qty at $10/pcs for the same material
Price = 500*10
= 5000$
Standard Price : It doesn't change with the change in price in new PO, so suppose the standard price maintained in material master was 20$ when 1st goods are received
total value = total stock * Standard price
= 600qty * 20$
= 12000$
Moving Average Price : It does change with the change in price in new PO, so suppose the moving price maintained in material master was 20$ when 1st goods are received
total value = total stock * Moving avg price
MAP = total value / total stock
= 7000$ / 600qty
= 11.6666666667 $